School Building Project
State Street School
Springbrook School
Dunns Corner School
Main Project Status Update
•TOWN OF WESTERLY – 5/2
•NOTICE OF AWARD
•TOWN OF WESTERLY – START 5/2
•OWNER/GC CONTRACT – AIA A101
•REVIEW BY TOWN SOLICITOR
•SIGNED BY ALL PARTIES
•GC TO ISSUE CONTRACTS TO SUBS – MAY
•SUBMIT DOCUMENTS FOR PERMIT – MAY
•CONST SUBMITTALS START – MAY
•CONST. PHASING W/ GC & ADMIN – MAY
•PACKING AND PREP OF SCHOOLS – JUNE
•GC MOBILIZATION ON SITES – 6/21
•CONSTRUCTION START – 7/1